Compute the Average Turn Around Time of the following process scheduling algorithm.
Arrival Time: 0 1 2 3 4 5 6 7 8 9 10
Job Name: A B C D E F G H I J K
CPU Cycle: 5 2 8 4 3 1 2 9 7 3 4
Time Quantum: 2
ANSWERS:
a. a. FCFS
Job A | Job B | Job C | Job D | Job E | Job F | Job G | Job H | Job I | Job J | Job K |
0-5 | 7 | 15 | 19 | 22 | 23 | 25 | 34 | 41 | 44 | 48 |
ATT = 5+7+15+19+22+23+25+34+41+44+48 = 25.73
11
b. b. SJN
Job F | Job B | Job G | Job E | Job J | Job D | Job K | Job A | Job I | Job C | Job H |
0-1 | 3 | 5 | 8 | 11 | 15 | 19 | 24 | 31 | 39 | 48 |
ATT = 1+3+5+8+11+15+19+24+31+39+48 = 18.55
11
c. SRT
Job A | Job B | Job C | Job D | Job F | Job G | Job E | Job H | Job I | Job J | Job A | Job K | Job I | Job C | Job H |
0-1 | 3 | 4 | 8 | 9 | 11 | 13 | 14 | 15 | 18 | 22 | 26 | 32 | 39 | 47 |
ATT = 22+2+2+5+9+5+5+40+24+9+16 = 12.64
11
d. Round Robin
Job A | Job B | Job C | Job D | Job E | Job F | Job G | Job H | Job I | Job J | Job K | Job A | Job C | Job D | Job E | Job H | Job I |
0-2 | 4 | 6 | 8 | 10 | 11 | 13 | 15 | 17 | 19 | 21 | 23 | 25 | 27 | 28 | 30 | 32 |
Job J | Job K | Job A | Job C | Job H | Job I | Job C | Job H | Job I | Job H |
33 | 35 | 36 | 38 | 40 | 42 | 44 | 46 | 47 | 48 |
ATT = 36+3+42+24+24+6+7+41+39+24+25 = 24.64
11